Paragon Road Section Resurfacing

Paragon Road Section Resurfacing
Posted on 05/09/2019

Road Construction for Sections of Paragon and Sheehan Roads

Road construction is taking place on Paragon Road north of Social Row Road and also on Sheehan Road as part of the Randall Residence Development.

The development’s contractor, in cooperation with Washington Township and the City of Centerville, is performing roadway improvements on Paragon between Social Row Road and 300 feet south of Mackenzie Court and on the west side of Sheehan  between Social Row and the Centerville Bus Garage.

  • Work scheduled for July 1 & 2 - will consist of milling the roadway surface on Paragon and the west side of Sheehan. Construction during this phase will utilize traffic flagging to maintain traffic.

  • Work scheduled for July 2 & 3 - will consist of placing finished pavement on the milled surfaces. Construction during this phase will utilize traffic flagging to maintain traffic. 

  • July 5 & 6 - are back-up dates for weather delays.

  • Traffic striping will be replaced following the surface course completion.

Additional updates will be provided if these dates are adjusted due to weather conditions.