Washington TownshipMontgomery County, Ohio

Mad River Bridge Project

Mad River Bridge Project
Posted on 07/10/2019

Mad River Road Bridge Reconstruction 

Mad River Road is now open following bridge replacement south of Alex-Bell Road.

Information about the Mad River Road Bridge Reconstruction project is posted on this page. The bridge is located on Mad River Road, immediately south of Alex-Bell Road and north of Munger Road and Yankee Street. 


 October 16 -

Weather permitting, Mad River Road is scheduled to reopen to traffic on Thursday, October 17. The temporary traffic signal installed at the intersection of Alex-Bell and Munger roads is scheduled to be removed the week of October 21.


 

 Mad River Road Bridge  Mad River Road Bridge

October 11 -
The replacement of guardrails is underway. Bridge construction is nearing completion.





 

 Mad River Road Bridge

 

October 7 -
Paving was completed last Friday. Now just a few more tasks -- including guardrails and striping -- are required. If the weather cooperates, the bridge will be open in a couple weeks!

 Mad River Road Bridge



 

Mad River Road Bridge Mad River Road Bridge

September 26 -

Once its beams are set and the concrete deck is poured, the bridge is ready for its approach slabs to be added. These photos show work being done to construct the slabs which provide a smooth connection between the bridge and the road.



 Before photo  After photo

September 19 -

What a difference a day can make! On Wednesday, equipment to pour the concrete deck was being tested. By Thursday, the bridge's deck had been poured.

 Wednesday  Thursday  



 

September 6 -

The construction of Mad River Road bridge is going well and, so far, is on schedule. The bridge beams are set and work is beginning on forming the concrete deck and associated peripherals. There is still a lot of work to go, but the project is progressing well.

Mad River Road Bridge


 


 

Mad River Road Bridge Mad River Road Bridge

August 29 -

Beams have been placed across two of the bridge's three spans. The third span is anticipated to be completed on Friday.

Mad River Road Bridge



 

 Bridge work

August 20 -

Work on the Mad River bridge project continued this week -- even in the rain. The project remains on schedule.




 

August 13 Update -
Bridge deck is removed and the crew is now removing unsound concrete from the piers and back walls. This operation should take about another week.

 
 Mad River Road Bridge
Mad River Road Bridge Mad River Road Bridge

 


 

Bridge workAugust 6 Update -
The old bridge is coming down over the next few weeks, starting with the guard rail and then the beams.


August 5 Update -
Mad River Road bridge closes for approximately 90 days.


July 26 Update -
The southbound lane of Mad River between Alex-Bell and Munger will be open to traffic on Saturday, July 27. Both lanes will remain open through August 4. On August 5, both lanes of Mad River between Alex-Bell and Munger will close in order for bridge replacement to take place.


July 18 Update -

DP&L has reported that the work to relocate poles and electric lines will continue into next week. Both lanes of Mad River Road will be open to traffic Saturday, July 20, through Monday, July 22. However, the detour for the southbound lane of Mad River Road between Munger Road and Alex Bell Road will resume Tuesday, July 23. Closure is expected to continue through Friday, July 26.


 

July 11 Update -
The southbound lane of Mad River Road from Alex-Bell to Munger is slated for closure Tuesday, July 16, through Thursday, July 18, so that utilities can be relocated prior to bridge reconstruction. As with all project closures, this is weather permitting. Northbound traffic will be allowed to use the bridge.

Following utility relocation, the road will fully re-open until bridge replacement begins. Starting August 5, the road (including both lanes) will be closed for bridge replacement.


Reconstruction of the bridge on Mad River Road is a project of the Montgomery County Engineer's Office.

 Montgomery County Engineer's Office
Mad River Road Bridge Project Information
(
937) 225-4904
 Project Engineer
Rex Dickey
 Construction Engineer
Daniel Medeiros